The first element of the Fehmarn Belt Tunnel between Germany and Denmark could be lowered off the Danish island of Lolland as early as this spring, Danish state-owned construction company Sund & Bælt said on Thursday.
A special vessel that is to sink the tunnel elements has been approved by the Danish Maritime Authority, the company said.
The ship's task was "complex, so numerous tests were necessary," deputy contract director Lasse Vester said in the statement. "Now we have received approval for the ship and can start lowering it."
The construction consortium Femern Link Contractors (FLC) can now begin the necessary preparations, it said.
In January, Sund & Bælt said the opening of the 18-kilometre tunnel was likely to be delayed until 2031, partly because of missing permits. Once the first tunnel elements have been sunk, a new timetable will be drawn up, it had now said.
Huge infrastructure project
According to Sund & Bælt, the Fehmarnbelt Tunnel for cars and trains is one of Europe's largest infrastructure projects. It will eventually connect the German island of Fehmarn with the Danish island of Lolland.
On the German side, a hinterland connection is being built that also includes the Fehmarn Sound Tunnel between the island and the German mainland.
LATEST POSTS
- 1
13 must-see moon events in 2026: Eclipses, supermoons, conjunctions and more - 2
Doritos and Cheetos debut 'NKD' options, without artificial colors or flavors - 3
These Are the Journalists Israel Has Killed Since the Start of the Iran War - 4
Family Matters: Tips and Guidance for Effective Nurturing and Everyday Life - 5
Senegal limits foreign trips for officials as the fallout from Iran war deepens
Becoming Familiar with an Unknown dialect: My Language Learning Excursion
The Development of Shipping: Controlling Towards a More Associated Future
Colombia's military rescues 6 siblings who hid in the rainforest to escape from a rebel group
Americans generally like wolves − except when we’re reminded of our politics
Moderna to complete US mRNA manufacturing network with $140 million investment
Car Investigation: A Survey of \Past the Outside\ Car
Flu is rising rapidly, driven by a new variant. Here's what to know
West Antarctica’s history of rapid melting foretells sudden shifts in continent’s ‘catastrophic’ geology
12 times rockets and spacecraft crashed and burned in 2025